October 03 2018 0comment
Goda Bottle and Glass Factory Project well under progress (1-10-2018)

Construction of Goda Bottle and Glass Factory Project well under progress

Project Client and Consultant

Goda Bottle and Glass Factory and K2N Architecture & Engineering Consultancy Plc are the clients and consultants of the project respectively.

Contractor

ASER Construction Plc

Project Description

• The scope of the project consists construction ofOffice Building, Clinic Building, Canteen Building, Dormitory building, Site work, internal road, landscaping and drainage, Different types of factory plant buildings, Different types of raw material and product stores and Water treatment Area circulation water station shade.
Current Project Status
As of August 30, 2018 major works of Goda Bottle and Glass Factory Project reaches about 17% in overall status. Financially 21% has been executed for plant buildings & 8% for non-plant buildings.

Project Work Force

The project currently provides job opportunity for 65 permanent and 286 temporary workers.