SANSUSI TATEK –KELA PROJECT IN PROGRESS 18.6 % HAS BEEN COMPLETED

On April 26,2017 ASER has signed sansusi tatek- kela road project in BURAYU city administration of Oromia regional state work various activities even though delay the schedule.

Currently status of project reaches 18.6% which is Birr amount mentioned 108.205.90 over all progress on going works are structure, concrete pipe installation, asphalt placing, base course and sub-base Asphalt placing cover 2.41 km left hand side half of the road.

The major constraint to delay the progress are weather condition, design delay, distribution of peace instability of the country & right off way in order to this Ethiopia Road Authority pay compensation for EEPCO, water line & give away street house, but they didn’t remove from the furtherance road.