SANSUSI TATEK – KELA PROJECT WELL UNDER PROGRESS

ASER construction plc covers 22.5% of the total Construction work undertaken Sansusi Tatek – Kela Road work project. meanwhile, the following activities have been performed earthwork, drainage, borrow to fill, cut to spoil & rock fill. On the other hand, give away street house taking off and 2.57 km asphalt binder course placing, structures, back fill 4.8 km, & 12 box culverts are completed right side the road. Sub base and road base & gravel wearing course construction works reaches 13.31% respectively. Besides, other minor obstruction right of way, design delay & quarry site problem the main issue. Accordingly, 106 temporary & 33 permanent employees get job opportunities.