September 19 2015 0Comment

Construction of Sewer Line for Bethel Area

Project Name 

Construction of New Sewer Lines for Betel Area and Re-sizing of the existing Lines Project.

 Site Handover

ASER Construction Plc. took over the Project Site and Commenced Operation in June 2015.

Project Description 

Project works includes Construction of a total of 27.12Km of New Sewer Lines and re-sizing 4.34Km of the existing trunk Sewer Lines from manhole MW-KL.

Work Under Progress

The Work under Progress consists of Clearing of the Site, Excavation up-to Sub grade level, slope stack excavation, Removal and Replacing of Existing Walls and Fences.

Client and Consultant

The Client of the Project is Addis Ababa Water & Sewerage Authority Water & Sanitation Development and Rehabilitation Project Office and SWS Consultancy Plc. is the Consulting Firm.

Contractors

ASER Construction Plc and IFH Engineering Plc in Joint Venture.

Project Work Force

The project provides job opportunity for 24 permanent and temporary workers of which 7 are female.

admin