October 27 2015 0Comment

Kilinto and Koye-Fiche Water Supply Project

Project Name

Supply and Installation of Pipes and Fittings and Construction of Civil works of Kilinto and Koye-Fiche area Water Supply Project(from well field Koye Reservoir) Contract-I. 

Work Status
Besides concrete casting and concrete work at both Koye 10000m3 and CT-2500m3 reservoirs, currently transmission line (DCI Pipe laying under express way through box culvert) and setting out generator shelter layout, excavation for generator house, selecting material fills and masonry work, lean concrete work, grade beam and slab reinforcement bar placing works for control room is under construction.

Project Work Force 

The project provides job opportunity for 230 permanent and temporary workers of which 12 are female.

 