January 04 2016 0Comment

Sewer Line Construction for Betel Area

Project Name

Construction of New Sewer Lines for Betel Area and Re-sizing of the existing Lines MW-KL Project.

Client and Consultant

Addis Ababa Water & Sewerage Authority Water & Sanitation Development and Rehabilitation Project Office is the Client whereas, SWS Consultancy Plc is the Consulting firm of the Project.

Contractors

ASER Construction Plc and IFH Engineering Plc in joint venture.

Scope of the Project

Scope of the Project includes construction of a total of 27.12Km of New Sewer Lines and Re-Sizing 4.34Km of the existing trunk Sewer Lines from manhole MW-KL.

Work Under Progress

All the survey activities are completed and construction of access road and platforms are also under well progress.

Major Problems

Major problems, among others, are related with right of ways issues (right of way obstruction) and delay in LC opening by the Employer for GRP Pipe and other accessories importation.

Project Work Force

The project currently provides  job opportunity for 26 permanent and 58 temporary workers.

Machinery Utilization

A total of 16 heavy and small machinery’s are currently deployed for the project.

Project Impact

Besides contributing to the proper management of sewerage of the area, the project provides substantial job opportunity.