Kilinto and Koye Fiche Water Supply Project

Project Name

Supply and Installation of Pipes and Fittings and Construction of Civil works of Kilinto and Koye-Fiche area Water Supply Project(from well field Koye Reservoir) Contract-I.

Project Description

A contractual agreement signed between ASER Construction plc and Addis Ababa Water and Sewerage Authority and Sanitation Development Project Office to supply and install pipes and fittings including civil work construction from well field to koye reservoir on the 20th of May, 2015.

Progress Status

83 percent of the works of koye 10,000m3 service reservoirs is completed while 60 percent on CT-5 2,500m3 service reservoirs has already been finalized.

The works of transmission and collector line have reached 15 and 51 percent respectively. And a total of 1,488m collector pipe line (which is 21 percent of the total line) is so far completed.

By February 2016, more than 40 percent of the physical status of the project has been executed.

Client and Consultant

Sanitation Development and Rehabilitation Project Office of the Addis Ababa Water and Sewerage Authority and the Consulting firm Oromia Water Works Design and Supervision Enterprise (OWWDSE) are the client and the consulting firms respectively.

Project Duration

The duration of the project is 365 calendar days.

Project Work Force

Currently, a total of 141 workers are engaged on the project; out of which 33 of them are permanent and the remaining 108 casual.