Project Name
Construction of New Sewer Lines for Betel Area and Re-sizing of existing trunk Lines MW-KL Project.
Client and Consultant
Addis Ababa Water & Sewerage Authority Water & Sanitation Development and Rehabilitation Project Office is the Client whereas, SWS Consultancy Plc is the Consulting firm of the Project.
Contractors
ASER Construction Plc in joint venture with IFH Engineering Plc
Commencement Date
ASER Construction Plc. took over the Project Site and Commenced Operation in June 2015.
Scope of the Project
Scope of the Project includes construction of a total of 27.12Km of New Sewer Lines and Re-Sizing 4.34Km of the existing trunk Sewer Lines from manhole MW-KL.
Work under Progress
As of September 29, 2016 plat form construction activities of site clearing, excavation up to sub grade level are well under progress for the five kilometer and nearly 95 percent has been completed while trench excavation activities for the same area has been finalized.
Current Project Status
By the end of September 2016, 14.5 percent of the physical status of the total work has already been completed.
Project Work Force
The project currently provides job opportunity for 75 permanent and 226 temporary workers.
Machinery Mobilization
A total of 40 heavy and small machinery’s are currently deployed for the project.
Project Impact
Besides contributing to the proper management of sewerage of the area, the project provides substantial job opportunity for significant number of workforce.