Project Name
Bole Ring Road RBT – Meskel Square Wello Sefer-Urael Supplementary Road Project
Scope of the Project
Scope of the project encompasses road construction of a total of 1.7 km that traverse from Wello Sefer to Urael. The main works of the project includes box culvert construction with a 15.6 height with a 10m span and 36 of width and construction of retaining walls of 12m height. Excavation, capping, sub-base and base course works including excavation for drainage and utility works are also part of the project.
Current Work Progress
The project work is being under taken in two separate sites; one at Peackok side that encompasses 400 m and the other from Urael Atlas side and this comprises 200m. As of early December, 2016 the total status of earthworks, pavement works and structure works has been reached 88 percent.
Client and Consultant
Addis Ababa City Roads Authority (AACRA) is the client while Engineer Zewdie Eskinder and Co. PLC is the consulting firm.
Contractors
IFH Engineering Plc is the main Contractor while ASER Construction Plc is Sub-Contractor of the Project.
Machinery Mobilization
A total of around 10 Machinery’s and Equipment’s are deployed for the project.
Project Work Force
Currently a total of 58 workers are engaged on the project of which 9 employees are permanent and the rest 49 are temporary.