ASER undertaking Megenagna lot 1 and 2 Road Project -Megenegna Taxi Bay supplementary project

Project Name

Megenagna lot 1 and 2 Road Project -Megenegna Taxi Bay supplementary project

Scope of the Project

Scope of the work encompasses immense excavation, capping, sub base and base course works including asphalt overlay as well as a 556 m pipe laying works.

Client and Consultant

Addis Ababa City Roads Authority (AACRA) is the client while Core consulting Engineers PLC is the consulting firm.

Contractors

IFH Engineering Plc and ASER Construction Plc.

Commencement Date

February 4, 2017

Machinery Mobilization

A total of 37 Machinery’s and Equipment’s are deployed for the project.

Project Work Force

Currently a total of 92 workers are engaged on the project of which 20 employees are permanent and the rest 72 are temporary.