March 09 2017 0Comment

58 % of Construction of Sewerage Line for Betel area has completed

Project Name

Construction of New Sewer Lines for Betel Area and Re-sizing of existing trunk Lines MW-KL Project.

Client and Consultant

Addis Ababa Water & Sewerage Authority Water & Sanitation Development and Rehabilitation Project Office is the Client whereas, SWS Consultancy Plc is the Consulting firm of the Project.

Contractors

ASER Construction Plc in joint venture with IFH Engineering Plc

Commencement Date

ASER Construction Plc. took over the Project Site and Commenced Operation in June 2015.

 

 Scope of the Project

Scope of the Project includes construction of a total of 27.12Km of New Sewer Lines and Re-Sizing 4.34Km of the existing trunk Sewer Lines from manhole MW-KL.

Work under Progress

Currently plat form excavation and fill work has been reached 96 and 46 percent respectively while 75 percent of trench and pipe installation has been completed and other substantial works are also well under progress.

Current Project Status

As of early March, 2017, out of the total scope 18.5 km of has been completed as a result 58 percent of it is accomplished.

Project Work Force

The project currently provides job opportunity for 66 permanent and 452 temporary workers.

Machinery Mobilization

A total of 61 heavy and small machinery’s are currently deployed for the project.

pr-admin

Write a Reply or Comment