Koka-Adulala-Debrezeit Design and Build Road Project

Project Name

Koka-Adulala-Debrezeit Design and Build Road Project.

Project Client and Consultant

Ethiopian Roads Authority (ERA) and NET Consulting Engineers & Architects Plc. respectively are the clients and consultants of the Project respectively.

Contractor

ASER Construction Plc

Project Description

The Design and Build road project extends from Modjo town branching to the right from the existing Modjo-Hawassa trunk road at the exit of Koka town and traverses through Dire town; then it crosses in the North-East direction to terminate at Debrezeit town. The Project involves Design and Construction of Asphalt Concrete Road Project having a total design length of 52.22Km.

Current Project Status

As of march 10, 2017 major works of clearance and earth work as well as sub base works has been completed 99 and 56 percents respectively while bridge, slab culvert, pipe culvert and drainage works has completed 99, 98, 100 and  41 percents respectively. Complete asphalt overlay works for 16 km of the road has been completed so far.  As a result 65.7 percent of the total work of the project has been completed.

Machinery Mobilization

ASER Construction has currently mobilized a total of 247 construction machineries and Equipments.

Work Force

Currently, a total of 717 work forces are engaged on the project; out of which 129 are permanent and the rest 588 are temporary workers.