Project Name
Supply and Installation of Pipes and Fittings and Construction of Civil works of Kilinto and Koye-Fiche area Water Supply
Project Description
Supply and install pipes and fittings including civil work construction from well field to koye reservoir.
Client and Consultant
Client of the project is Addis Ababa & Sewerage Authority Water & Sanitation Development and Rehabilitation Project Office. Oromia Water Works Design and Supervision Enterprise (OWWDSE) is the consulting firm.
Commencement Date
ASER Construction Plc. took over the project site and commenced operation in early June 2015.
Project Location
Akaki Kality, Addis Ababa
Current Project Progress
As of late march, 2017 the physical status of the project has been reached 97 percent and all the project works will be completed before the march 15, 2017 and hopefully the handover ceremony will be held on March 17, 2017.
Project Handover
ASER will hand over the project site on project 17 April 2017.
Project Work Force
Currently a total of 21 and 71 permanent and temporary employees are respectively engaged on the final steps of the project.
Machinery Mobilization
A total of 12 machineries are currently deployed for the project.