SANF Water Supply Project

Project Name

Supply and Installation of Pipes and Fittings, and Civil Works Construction of South Ayat North Fanta (SANF) Water Supply Project

Scope of the Project

The scope of the project consists of supply and installation of pipe and fittings and Civil work constructions of laying various diameter DCI collector pipes in SANF well fields (21Boreholes), construction of ground level construction of ground level reinforced concrete reservoirs of capacity 10,000m3 and 5000m3 collection tank (CT5) around Tulu Guddo, construction of road, watercourse and other crossings, and construction of other miscellaneous works.

Commencement Date and Duration

ASER Construction Plc. took over the project site and commenced operation on November 7, 2016 while the project duration is 365 calendar days.

Current Project Progress

As of March 30, 2017 excavation works are well under progress for reservoirs of capacity 10,000m3 and 5000m3 collection tank (CT5) around Tulu Guddo and 8 and 5 percent of the physical status of the reservoirs has been completed sofar while construction of Ancillary Buildings at Tullo Guddo siite work has been completed 4 Percent.

Project Work Force

The project currently provides job opportunity for 7 permanent and 93 temporary workers.

Machinery Mobilization

A total of 10 heavy and small machinery’s are currently deployed for the project.