Project Name
Construction works of internal road first layer works & asphalt overlay works of Anbessa garage.
Project Client
Addis Ababa City Transport Authority
Contractor
YOTEK Construction & ASER Construction PLC
Project Description
The project scope includes construction of 8,500 m2 first layer works & 5,000 m2 concrete asphalt overlay work.
Project Location
Addis Ababa
Current Project Status
As of July 10, 2017 construction of asphalt overlay for more than 95.3% has been completed and the total work is expected to be completed at the end of next week.
Machinery Mobilization and Work Force
A total of 18 machineries & Trucks are deployed and 25 work forces are engaged on the project work.