ASER is undertaking the Kaliti RRI- Tulu Dimtu Roundabout Road Project (Lot-1)& Kaliti RR- Bulbula Kilinto Roundabout Road Project (Lot-2) as sub-contractor from China Communications Construction Company (CCCC).
The Two projects cover a length of 6.05 km & 3 km respectively which will have carriage way, bicycle lane & a walk way alongside to the main road. Earth work, pavement works, construction of over bridge, installation of longitudinal drainage pipes & other similar works are the main duties of ASER. Currently building culverts, excavation for underpass & bridge foundations and similar tasks are being done.
Duration to complete & handover projects for the main contractor will be within 720 calendar days.
As of December 11, 2017 project status for both Lot-1 & Lot-2 has reached 7% and 3% correspondingly.
AACRA is the client for both lot-1 & lot-2.
Machinery Mobilization and Work Force
A total of 160 machineries & Trucks are deployed and 162 work forces are engaged on the two projects.