SANSUSI TATEK-KELA PROJECT WORK UNDER PROGRESS

Work under progress is augmented like never before. ASER construction team is now working day & night to finish the project on the scheduled time line. Some complications regarding delay of construction work are being resolved now.
Currently the following works are being under construction
• 3 box culverts are finished
• 2 box culverts are under construction
• 7 pipe culverts are finished except inlet head wall
• Three pipe culverts are under construction
• Excavation of unsuitable material and replacement with suitable material from 5.4 km to 13.4 km well underway
• Side drainage pipe laying from 11.79 km to 12.35 is well underway
Beside other minor obstructions Right Of Way problem is still the main issue.