Previously ASER has signed a contract six-Addis Ababa city River crossing steel bridge project to construct. The scope of the project builds a river crossing steel bridge and pipe installation. Currently, the total status of all project reaches 81%. Besides, to this separately describes the project status Posta bet, Begetera, Chefe genet are accomplished. And also, Mecharameda & Lebu project reaches 90%, the remaining project Afinchober 55 % presently, the Project includes construction 3.48 km pipe installation and construction of pier well under progress. On other hand, this project avoids river pollution. due to this, waste sewage pass inside the pipe addressed managing recycling & pollution prevention & eliminating harmful environment. In addition to this, currently a total of 49 workers are engaged in the project which is 40 employees are temporary & 9 permanent.