June 25 2020 0comment

ASSAITA-AFAMBO TO THE DJIBOUTI BORDER ROAD PROJECT PROGRESS REACHES 10 %

ASER has worked a road Construction from Assaita Afambo to the Djibouti border road project. The main duties ASER to construct Asphalt road covers a length of 49 km respectively. Currently, major activities describe all contractor’s and Consultant’s camp completed and all employees are accommodated in the camp, Both Embankment and Excavation of Roadway started and accomplished 10% so far, Slab culvert, pipe culvert and retaining wall activities started and progressed well, Afambo lake now accessible, Reinforced pipe and sub-base material stock available at the site. on the other hand, a total of 33 pieces of machinery & 147 trucks is deployed and 141 permanent and 715 temporary work forces are engaged on the project.