BOLE MICHAEL RING ROAD OVERPASS AND NEARBY APPROACH ROAD PROJECT PROGRESS REACH 18%

ASER has signed a contract agreement with Addis Ababa City Roads Authority in the sum of 867,909,348.53 birr for the construction of Bole Michael ring road overpass and nearby approach road project. Currently, the physical status of the project describes. Road 2A & 2 stations approximately 1 km, roundabout (0.36 km) and road 2B (0.78 km) roads are completed and also, earthwork, pipe side drainage, utilities lines work (Tele, AAWSA and EEPCO), slab culvert, protection work (retaining wall), asphalt pavement binder course similar tasks are being done. According to this project, progress reaches 18%. besides this, it creates a job opportunity for 35 permanent & 157 temporary employees. On the other hand, the main work of the project ring road construction extended to the next new year due to a reason for a right of way issue & unsuitable rainy season.