The Construction of the Bole Michael ring road overpass and nearby approach road project main work activities underway.
In an exclusive interview on Nov2, 2020, Construction Engineer Fisseha Hapitye said “ previously, we are working on the construction of tributary roads. Road 2, 2B & 1. The Construction of road 2B half of the road asphalt placing and the remain part riches Base course & sub-base level. Road 2&1 excavation, pipe installationfill work, sub-base & road bases almost done. Side by side, utility line & electrical works under progress. And also, the main work of this project ring road has started working. According to this, current activity describes sub-base, culvert, excavation, walkway, retaining wall, pier installation, well under progress. Overall, we are working full of energy & resource but, due to right of way issue and design change, 48% elapsed the schedule. Accordingly, the total status of the project richesabove19 %. Besides, it creates a job opportunity for 37 permeant and 101 temporary workers. “