November 27 2020 0comment

ASER OPEN PROJECT CAMP AND START GIVING SERVICE

The Legedadi Phase II water Supply Project Administration Prepares the Camp’s well-coming program for works.

Now 24,2020 the project of Legadadi Phase II water supply project & construction opens the camp and start giving service for the permanent employees. In an exclusive interview on Nov 24, 2020 Project Manager Kinfemichael Aregay Said ` the Project location far from Addis Ababa around 40km to this, ASER Construction P.L.C open a camp on the project area Oromia national regional state Legebri -Legadadi to make comfortable work environment for the Permanents Employees. And also, the camp has dormitory and cafeteria services.

According to this, currently, all activities underway this meant both Lc1 and Lc2 reservoir roof slabs the final step and Oromia national regional state Sendafa station burrow hole work under completion & 12km pipeline extended …etc.

Access road work delay due to right of way issue and critical problem of civil work. Besides this, ASER submits the client rate change to construct quality and long-lasting road. Presently, the client summarized the rate which is waiting for the output to start working.

Side by side, it creates a job opportunity for 38 permanents in this situation labor skilled transfer and 190 temporary works upgrading themselves from the senior labor. Overall, the access road work expects generating economy of the surrounding community and different vehicle beneficiary. ̎

PR Admin