BOLE MICHAEL RING ROAD OVERPASS AND NEARBY APPROACH ROAD PROJECT IN PROGRESS 28% BEEN COMPLETED

ASER has signed a contract agreement with Addis Ababa City Roads Authority in the sum of 867,909,348.53 birr for the construction of Bole Michael ring road overpass and nearby approach road project. Currently, the physical status of the project describes. Road 2A & 2 stations and road 2B roads are the fist layer asphalt completed and also, earthwork, pipe side drainage, utilities lines work (Tele, AAWSA and EEPCO), slab culvert, protection work (retaining wall), asphalt pavement binder course similar tasks are being done. According to this project, progress reaches 28%. Besides this, it creates a job opportunity for 35 permanent & 245 temporary employees. On the other hand, the main work of the project ring road construction has completed