TULU DIMTU – KALITI PIPE RELOCATION ROAD PROJECT

On Aug 7, 2019 ASER was granted a contract from ADDIS ABABA water and sewerage authority (AAWSA) in the sum of 66,680, 786, 64 birr for the TULU DIMTU -KALITI pipe relocation road project.

Currently, the physical status of the project describes, the right side of Road pipe installation and under bridge installation are binge done. According to this project progress reaches 15%.the major constraint to delay the progress are due to the lack of foreign exchange, the DCI pipe was not available for the project. Besides this, it creates for local community job opportunity for 12 permanent and 34 temporary employees.