December 23 2022 0Comment

Bole Homes- Gumuruk Ring Road Project 31.45 % completed

One of the road construction projects being built by ASER Construction is Bole Gumuruk Ring road project.

It has a length of 4.9km and a side width of 30 to 60 meters.

Currently the project status reaches 31. 45%.

Till now 2.8 km on RHS asphalt and 1.28Km on LHS asphalt completed and opened for traffic. RHS Bridge at km 2+100 and earth work construction is under progress.

Addis Ababa city Road Authority (AACRA) is the client and United Consulting Engineers P.L.C (UNICONE) is the consultants of the project.

The project gave job opportunities for 44 permanent and 131 temporary employees.